Order Notation (Interval and Quantity)
|
||
|
d - average demand (daily, weekly or monthly)
|
s – variable ordering costs (per SKU)
|
S – fixed order processing costs
|
|
z – safety stock factor – number of std deviations above expected demand
|
n – number of SKUs purchased from the supplier
|
D(j) – annual demand of SKU(j)
|
|
LT – lead time (daily, weekly or monthly)
|
n – number of SKUs purchased from the supplier
|
OI – order interval (time between orders) (daily, weekly or monthly)
|
|
σ(d) – standard deviation of daily, weekly or monthly demand
|
i – annual holding cost rate
|
R(j) – unit cost per SKU(j)
|
|
BOM that identifies the dependent parts needs for one unit of finished good. A listing of all raw materials, sub assemblies and parts.
|
|
Master Production Schedule (MPS) to determine how much will be made and when it will be made.
|
|
A list of any existing inventory of each good on the BOM.
|
|
Estimated lead time requirements for individual components (from suppliers).
|
|
A list of any existing open orders for any of the components needed to avoid duplication.
|
|
Lot-for-lot ordering: Determine orders based on requirements
|
|
Lot-size ordering: planned receipts may exceed net requirements
|
|
Planned-Order Receipt: Quantity of an order to be received at the beginning of a period
|
|
Planned-Order Release: Quantity planned to be released (purchased) at the beginning of a period. Planned-order release = planned-order receipt adjusted for lead time
|
|
Pegging: prcoess of identitifying the end product(s) manufactured from a specific part or input. Important in firms with many parts.
|