#Standard Changes are approved by the team leader. There is no lead time for standard changes. There is no requirement to wait for Change Management Approval
|
|
#Minor Changes are to be submitted at least 3 working days before implementation date. Must receive final Change Management Approval prior to the start time of the Change window.
|
|
#Significant Changes to be submitted by 15:00 hrs Monday for that week’s CAB Meeting. Change can only proceed after the change has been presented and approved in the CAB meeting
|
|
#Major Changes requires a minimum 30 days prior to implementation.
|
|
#Emergency - Break-fix changes to restore disrupted services. If not implemented immediately customer productivity is severely impacted.
|
|
#Urgent: Required within 1 working day if the change is not implemented, business productivity is significantly impaired. May be a requirement to meet operational, financial, legal, and statutory or government requirements. Urgent Changes require Department Manager approval to justify the urgency.
|
|
#High: Required within the next 5 working days if the change is not implemented, business productivity will be impaired.
|
|
#Medium: Required within the next 10 working days No current effect on business productivity or impact on the customer but possible future impact if change is not carried
|
|
#Low: Can wait 2 weeks or more No impact on customer service, financial, security or legal requirements; or currently a sufficient workaround exists or release is pending
|
|
Primary Contact : Kalai Meeran - 0467 493 931
|
|
Secondary Contact : Namal Perara - 0459 037 930
|