Project Monitoring and Control
|
1.
|
Produce project plan
|
|
2.
|
Monitor progress against plan
|
|
3.
|
Compare actual progress with planned progress
|
|
4.
|
Identify variations from the plan
|
|
5.
|
Apply corrective action as / if necessary
|
|
PMs role is day to day to apply minor corrections as required
|
|
|
Major corrections need to be referred to superiors
|
|
|
Tolerance – PMs authority to make changes or apply corrective action
|
|
|
Exception report – outlines problem and options for solution, given to the project board. Includes:
|
|
|
-
|
Background
|
|
-
|
Reasons why the exception arose
|
|
-
|
Options
|
|
-
|
Risks
|
|
-
|
Exception plans showing how the project needs to be amended to implement suggestions
|
|
-
|
Amended business case
|
|
-
|
Recommendations
|
|
Contingency pool – set of resources controlled by PM and can be allocated by PM as needed
|
|
|
Recommendations may include:
|
|
|
Work harder, longer or faster
|
Solve a short term problem or meet a deadline. Tired, stressed and demotivated staff. Increased costs if overtime paid
|
|
Increase resources
|
Adding more people in IT does not often increase productivity, often it decreases. Training takes time and uses current resources. Expensive.
|
|
Replan
|
Reallocate the time on tasks which took shorter than expected. Internal movement of staff at no extra cost.
|
|
Extend the time scale
|
Sensible option. Common choice, requires negotiation. Extending deadline often seen as weak management or the project being out of control. More expensive
|
|
Reduce scope
|
Deliverables removed or delayed until later. Does not reduce costs, but value to the user may be reduced
|
|
Terminate the project
|
If no other option is ok, this maybe the only sensible thing to do. Maybe politically unacceptable
|
|
What should we monitor?
|
Progress toward deliverables, products and milestones. Progress in the WBS. % complete. Resource usage. Expenditure. Scope and size of deliverables. Watch out for scope creep. Monitor quality.
|
|
How should we monitor?
|
|
|
Formal
|
Lay frequency, content and format out at the beginning of the project.
|
|
-
|
Advantage: get commitment from people in writing and establish routines
|
|
-
|
Disadvantage: reports maybe seen as an unproductive overhead. Staff need to be convinced of the value
|
|
-
|
Types: Written progress reports, email, progress meetings
|
|
Informal
|
Manager have an awareness of what team enduring
|
|
-
|
Advantage: more honest and faster communication of problems
|
|
-
|
Disadvantage: need to avoid micro managing
|
|
-
|
How: Chats with the team individually
|
|
AKA Checkpoint meetings
|
|
|
Weekly / agile might be daily
|
|
|
Report from team leader to PM will be prepared. AKA Checkpoint report
|
|
|
Agenda typically
|
|
|
-
|
Each team members progress against their plans
|
|
-
|
Reasons for variances
|
|
-
|
Expected progress – what each team member will do next
|
|
-
|
Current problems or issues
|
|
-
|
Possible future problems – may include risks from the risk register
|
|
Issues log: record issues in an issues log, which will be updated as they are resolved
|
|
|
Backlog list: In an agile project a backlog list of tasks completed and to be done would be updated
|
|
|
Projects are sometimes grouped into programmes, where a number of projects contribute to a set of overarching objectives
|
|
|
Freq
|
Less frequent
|
|
Agenda
|
Less detailed. More of a business focus than a project focus
|
|
No point in monitoring without control
|
|
|
Do through the reporting cycle
|
|
|
-
|
Problems reported in progress
|
|
-
|
Apply controls to bring it back on course (Move resources from non-critical to critical)
|
|
-
|
Review allocation of resources
|
|
-
|
Reduce scope
|
|
Important to understand
|
|
|
The people responsible for the project have the right to change the project objectives, not the project manager
|
|
|
The report to the steering committee
|
|
|
Intervals and topics in report need to conform to requirements of the recipients and the importance of what is being conveyed.
|
|
|
Obtain formal agreement on reporting procedures from all parties involved
|
|
Attendees
|
PM and project board members, perhaps a secretary
|
|
Freq
|
~monthly. Larger projects probably has less frequency of catch ups
|
|
Agenda
|
Similar as for team meeting
|
|
Report
|
Highlight report, supplied by PM
|
|
Highlight report - typically includes the following information
|
|
|
-
|
Details of progress against project plan
|
|
-
|
Current milestones achieved
|
|
-
|
Deliverables completed
|
|
-
|
Resource usage
|
|
-
|
Reasons for any deviations from the plan
|
|
-
|
New issues and unresolved issues
|
|
-
|
Changes to risks assessments
|
|
-
|
Plans for the next period and products to be delivered
|
|
-
|
Graphical representations of progress information
|
|
Gantt chart
|
|
|
You will need to compare the current situation with the original plan, so the details on the Gantt chart need to be baselined
|
|
|
-
|
Take a snapshot of the schedule at key points
|
|
-
|
Maybe several but an important one will be the final agreed schedule at the beginning of the project
|
|
Cumulative resource chart
|
|
|
-
|
Present usage details
|
|
-
|
Aka S curve chart
|
|
-
|
Data points: Expected expenditure & Actual expenditure
|
|
Earned value analysis (EVA)
|
|
|
-
|
See if we are ahead or behind time, and above or below budget
|
|
-
|
EVA shows budget originally allocated to completed items
|
|
-
|
When completed we can say value is earned
|